Wind energy capacity addition to be subdued in FY2020: ICRA

By April 23, 2020 3:00 pm IST

Wind energy capacity addition to be subdued in FY2020: ICRA
.

The wind power sector is facing significant challenges because of the delays in making payments by the state distribution utilities and the execution delays being faced by the projects bid out by the central nodal agencies and state distribution utilities. This apart, the tariff uncertainty for the wind power projects in Andhra Pradesh has affected the investor sentiments in the sector. This is also reflected in the slowdown in the tendering activity of wind power projects by 67 percent to 2.3 GW in CY2019 from 6.9 GW in CY2018. Moreover, many of the bids called by central nodal agencies remained undersubscribed. While the capacity addition is likely to improve on a fiscal year basis to about 2.5 GW in FY2020 from 1.6 GW in FY2019 on the back of large project backlog, achieving the 60 GW target set by the Government of India by December 2022 remains a challenge. In this context, ICRA has recently revised the outlook for the wind energy sector from stable to negative.

Throwing more light, Girishkumar Kadam, Sector Head & Vice President – Corporate Ratings, ICRA, says, “Against the 5 GW to be commissioned as of December 2019, as per the timelines provided under the bids awarded by the SECI, NTPC and state utilities, only about 2 GW is estimated to have been commissioned. Thus, the actual execution on ground has been hampered by delays in completion of land acquisition, securing transmission connectivity for interstate projects, financing challenges due to concerns over bid tariff viability, and delays in approval for tariff adoption from the regulators.” Further, the bid tariff discovered in the recent wind power auctions continues to remain at less than `3 per unit and highly competitive against the conventional energy sources. The viability of these projects remains dependent upon the ability of the developers to identify locations and using wind turbine generator (WTG) machines having the potential to generate power at annual PLF of 35 percent or higher.

Advertising

EPR Android App Banner

Commenting on the PLF trend of the new turbines of MW class with hub height greater than 100 metres, Vikram V, Associate Head & Assistant Vice President – Corporate Ratings, ICRA says, “Our study of a sample set of projects commissioned over the past one to two years indicates that there are projects which have been able to achieve annual PLF in the range of 33– 38 percent, thus providing a comfort on PLF assumption which is critical for the viability of projects bid at tariffs lower than `3 per unit. Such projects typically have higher hub height and rotor diametre of more than 100 metres and are concentrated at windy locations in the states of Gujarat and Tamil Nadu. However, the sustainability of such performance over the long tenure also remains critical.”

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Tags: Power Update
Android App
Android App

Events

RenewX
RenewX
Wiretech 2025
Wiretech 2025
Power Gen
Power Gen
World Utilities Congress
World Utilities Congress
India Green Energy Expo
India Green Energy Expo

Our Sponsors

Wika
Wika
Ramelex
Ramelex
Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
Akansha
Akansha
Andritz Hydro Pvt Ltd
Andritz Hydro Pvt Ltd
Vyoma Switchgear
Vyoma Switchgear
Skipper Limited
Skipper Limited
Joint Well
Joint Well
Kp Group
Kp Group
Credence Solar
Credence Solar
Grew Solar
Grew Solar
Nirmal
Nirmal
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Novasys
Novasys
HPL Electric Power
HPL Electric Power
Sun Bond
Sun Bond
Supremesolar
Supremesolar
Vsole Solar
Vsole Solar
Elev8 Lift
Elev8 Lift
Power trac Group
Power trac Group
Omicron
Omicron
Ganz Electric
Ganz Electric
Eplan
Eplan
Aeron Composite Pvt Ltd
Aeron Composite Pvt Ltd
Eaton
Eaton
A-1 ELECTRICALS
A-1 ELECTRICALS
Ashone Technologies
Ashone Technologies
MENNEKES Electric India
MENNEKES Electric India
PRAMA HIKVISION INDIA
PRAMA HIKVISION INDIA
Motwane Manufacturing
Motwane Manufacturing
Sun Cables
Sun Cables