Promonique
Promonique
TCI
TCI
EPR Subscription Banner
EPR Subscription Banner
Home » EPR Personality » Better tariff, govt schemes to propel wind sector: IWPA

Better tariff, govt schemes to propel wind sector: IWPA

By August 27, 2020 11:11 am IST

Better tariff, govt schemes to propel wind sector: IWPA
.

At a hub height of 100 metres, India has a wind energy potential of 302 GW; by increasing the hub height by another 20 metres, the potential will more than double to 695 GW. The opportunity, therefore, is huge.
Prof. Dr. K. Kasthurirangaian, Chairman, Indian Wind Power Association (IWPA)

Though the main bottleneck for wind energy deployment is the existing policy framework – both at the central and state levels, Prof. Dr. K. Kasthurirangaian, Chairman, IWPA believes, “With better tariffs and with government’s recent initiatives, we are likely to fare better compared to the last few years.”

Now that the Indian government targets 510 GW RE by 2030, where do we stand today?
We are glad to see that the target of 60 GW of hydro-electric power by 2030 has now been added to the earlier renewable energy (RE) target of 450 GW. Out of the 510 GW target, wind energy is to contribute 140 GW. As of 31st July 2020, the operational installed wind energy capacity is 37.94 GW. That leaves India in a position where 102.06 GW of wind energy is to be installed in 10 years, i.e. about 10 GW per year. But in 2019-20, we added only 2.06 GW. Wind installations added in the previous years were 1.48 GW in 2018-19 and 1.87 GW in 2017-18. What is relevant though is that in 2016-17, India added a massive 5.5 GW of wind energy capacity. India thus has the capability to scale up and meet the challenge.

At current prices, the investment required to install such a capacity would be to the tune of around Rs. 6.12 lakh crore per GW. Though the government has allowed 100 percent FDI in the RE sector under automatic route, the FDI received was only a fraction of the requirement, viz. Rs 11,053 crore in FY 2018-19 and Rs 9,700 crore in the first nine months of FY 2019-20. These figures pertain to the RE industry as a whole.

What is the main bottleneck for renewable energy deployment in India?
Rather than speaking for renewable energy as a whole, the Indian Wind Power Association (IWPA) shall restrict itself to talking about wind energy deployment. The main bottleneck for wind energy deployment is the existing policy framework – both at the central and state levels. To illustrate:

  • Since around 2017, discovered tariffs that emerge from reverse auctions by SECI that apply to projects of 50 MW and above are being “imposed” even on small investors in the sub-25 MW category, though the cost structures of the two are not even comparable. Whilst discovered tariffs could form the base, it would be better if there is a mark-up that addresses the differences in cost structure of the sub 25 MW category. Further, it would also be better if there is a like to like comparison of costs, including transmission costs, so that no element is left out.
  • SECI auctions for wind energy seem to concentrate only on Gujarat and Tamil Nadu – they leave out Andhra Pradesh, Karnataka, Madhya Pradesh, Maharashtra and Rajasthan, which are also “windy” states.
  • Land availability for implementation of wind energy projects is a problem; even when available, the process of land-use conversion takes much longer than the project time lines set by SECI; where SECI makes available land, it is in locations where even the foundation cannot be laid for putting up wind mills.
  • Advertising

    EPR Android App Banner

    Though the Electricity Grid Code stipulates “must-run” status for renewable energy, there is heavy curtailment of wind energy, even during the peak season, resulting in a negative IRR for generators with sale-to-board Power Purchase Agreements (PPAs). This makes the industry unattractive to potential investors.
  • Delayed payment to wind energy generators by cash-starved DISCOMs is yet another issue. This is being addressed through liquidity injection by the Central Government through Government Financing Companies like REC, PFC etc., though it is only an ad-hoc solution.
  • What often goes wrong is the imposition of impractical project execution timelines that do not take into consideration ground reality. We are hopeful that based on data analysis and feedback that the industry gives the Government from time to time, workable solutions will emerge.

What’s your take on the recent performance of India’s wind power sector? Is it making a comeback after a temporary slowdown?
The prospects are relatively better for the wind sector. The pace is steady now, after a state of flux and then of stagnancy. Till 2017, with government’s fiscal incentives coming to aid, a majority of the capacity addition happened because of investments by the small and medium segment of industries, especially for captive consumption. When independent power producers came on the scene, capacity addition showed a steep increase after 2013, peaking at 5.5 GW in 2017.

With the first reverse bid SECI auction in 2017, the scenario changed. The lower rates being quoted pushed the SME investors out of the scene. However, the situation is now improving given that tariffs have begun to increase to more realistic levels in the recent bids. With better tariffs and with government’s recent initiatives, we are likely to fare better compared to the last few years.

What’s your revival strategy?
The revival strategy focuses on the fundamentals – minimise investment risk, maximise return on investment. However, this is easier said than done. Minimising investment risk involves addressing issues like delayed payments to generators by DISCOMs, honouring PPA terms, intermittency and regulatory inconsistencies; maximising return on investment involves substantially increasing evacuation of wind energy, enhancing Capacity Utilisation Factor (CUF), realistic tariff fixation, reducing costs etc.

A point to be made is that by 2050, the International RE body IRENA projects that 86 percent of the world’s energy demand will be met from RE sources – 8,500 GW would come from solar power and 6,500 GW from wind power. At a hub height of 100 metres, India has a wind energy potential of 302 GW; by increasing the hub height by another 20 metres, the potential will more than double to 695 GW. The opportunity, therefore, is huge.

India’s per capita energy consumption at 1,149 kWh is just around 50 percent of the world average. With the advent of electrical vehicles, the government estimates that per capita consumption in India will double by 2030. Further, taking into consideration India’s demographic dividend of having a large population under 30 years of age, all with aspirational growth targets, the per capita consumption is likely to go up even further. So, apart from opportunity, the market for energy is also there.

In order to seize market share, there is a need to view the challenges faced holistically and to address them through systemic interventions. Using such an approach, IWPA is collaborating with all stakeholders, the focus being on recreating an enabling business environment that addresses the fundamentals – minimising risk and maximising return on investment.

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Android App
Android App
EPR eMagazine December 2024
EPR eMagazine December 2024
EPR eMagazine December 2024

Events

Elecxpo
Elecxpo
India Smart Utility Week
India Smart Utility Week
RenewX
RenewX

Our Sponsors

Amararaja
Amararaja
Ambica India
Ambica India
Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
Om Technical Solutions
Om Technical Solutions
NBC Bearings
NBC Bearings
Nirmal
Nirmal
Aramco Asia
Aramco Asia
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Lucy Electric
Lucy Electric
Elev8 Lift
Elev8 Lift
Synthesis Winding Technologies Pvt Ltd
Synthesis Winding Technologies Pvt Ltd
flir system
flir system
Omicron
Omicron
Polycab
Polycab
Electrotherment
Electrotherment
Aeron Composite Pvt Ltd
Aeron Composite Pvt Ltd
MENNEKES Electric India
MENNEKES Electric India
PRAMA HIKVISION INDIA
PRAMA HIKVISION INDIA
Automatic Electric Ltd
Automatic Electric Ltd