460MW Talcher thermal power station faces closure in Odisha

By January 18, 2021 4:19 pm IST

460MW Talcher thermal power station faces closure in Odisha
.

Odisha may well be staring at a huge power crisis from the beginning of 2021 as NTPC’s 460 MW Talcher Thermal Power Station (TTPS) faces closure from January 1 for failing to fulfill the environmental conditions laid by the Central Pollution Control Board (CPCB).

The CPCB had issued an ultimatum to the old power plants to take expedient steps to upgrade and meet the emission norms including solid particulate matter (SPM), sulphur and nitrogen content, otherwise, they would be liable to be closed from December 31 this year.

Advertising

EPR Android App Banner

₹ 50 lakh per MW, it would have cost TTPS a whopping  23,000 crore to fix the deficiencies. Hence, it decided to replace its existing plant with two new ones of 660 MW each in 2018. But the state government proved to be a stumbling block.

Even as the contract for the  9,000 crore project was awarded the same year, the state government delayed the project clearance till February this year. It is now too late for TTPS to execute the project and NTPC’s lack of interest in the same has only made matters worse, sources said. TTPS was built in two phases. In 1968, four units of 60 MW each were commissioned and two more 110 MW units followed in 1982. The plant was initially being managed by erstwhile Orissa State Electricity Board.

But owing to losses and less than 15 per cent plant load factor, it was sold to NTPC in 1995, when Biju Patnaik was the CM. NTPC had invested heavily on the plant for its renovation and modernisation in 2000 and its life was fixed up to March 2021 by the Central Electricity Authority. But, meanwhile, CPCB came up with new guidelines which has now put TTPS in dock. However, a top TTPS official struck a note of optimism saying, “There is an ultimatum but we are hopeful of its extension beyond the end of the current year.”

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Tags: News
Webinar
Webinar
Android App
Android App
EPR EMagazine February 2025
EPR eMagazine February 2025
EPR eMagazine February 2025

Events

RenewX
RenewX
Wiretech 2025
Wiretech 2025
India Green Energy Expo
India Green Energy Expo

Our Sponsors

Wika
Wika
Ramelex
Ramelex
Ambionics India
Ambionics India
Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
Om Technical Solutions
Om Technical Solutions
Harting
Harting
CyanConnode
CyanConnode
Hitachi Energy
Hitachi Energy
Doble Engineering
Doble Engineering
CSE Power
CSE Power
ACD Machine Control
ACD Machine Control
Kusam Meco
Kusam Meco
Nirmal
Nirmal
Apar Industries
Apar Industries
Aramco Asia
Aramco Asia
Axis Electrical
Axis Electrical
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Neo Tele Tronixl Pvt Ltd
Neo Tele Tronixl Pvt Ltd
ZIEHL ABEGG
ZIEHL ABEGG
Paras Wires
Paras Wires
Waa Cables
Waa Cables
Balaji Switchgears
Balaji Switchgears
AEW
AEW
Gloster Cables Limited
Gloster Cables Limited
Cabex India
Cabex India
Newtech Switchgear
Newtech Switchgear
Vsole Solar
Vsole Solar
Ai Earthing
Ai Earthing
Rectifiers & Electronics
Rectifiers & Electronics
Elev8 Lift
Elev8 Lift
Synthesis Winding Technologies Pvt Ltd
Synthesis Winding Technologies Pvt Ltd
flir system
flir system
Omicron
Omicron
CAT
CAT
ATS Group
ATS Group
Ganz Electric
Ganz Electric
Havells
Havells
Eplan
Eplan
Synergy Transformers
Synergy Transformers
Marosons Electricals
Marosons Electricals
Myriad Industrial Solutions
Myriad Industrial Solutions
EMR
EMR
Teknika
Teknika
AVR
AVR
Indian Transformers
Indian Transformers
Triveni Turbine ltd
Triveni Turbine ltd
Ultra Electric India
Ultra Electric India
Polycab
Polycab
Electrotherment
Electrotherment
Minilec Group
Minilec Group