Ganz Electric
Ganz Electric
TCI
TCI
Rayzon
Rayzon
Home » Tech View » Uncovering the invisible

Uncovering the invisible

By June 12, 2017 3:05 pm IST

Uncovering the invisible
.

Why the integrity of the ground grid needs to be checked

The grounding system is an important component for the correct function of a substation. When it is not in suitable condition, there is an increased safety risk for people and control and measurement equipment may be affected as well. Different standard tests give an indication of the overall functionality of the ground grid but they cannot determine the precise internal condition of the grid itself.

The commissioning and maintenance strategy for electrical substations normally includes testing that assesses the condition of the ground grid: Measurements of the soil resistivity are done during the design stage; ground grid impedance and step and touch voltages are checked regularly. However, these tests cannot reveal the condition of the grid’s connections that affect its continuity. Therefore, a ground grid integrity test should be done in order to assess it.

Invisible danger in older substations
The integrity test for the ground grid basically consists of verifying the continuity between two different points on the grid. It ensures that the internal connections within the grid are in a good enough condition to dissipate fault currents. Such a test is particularly important in older substations where the grid has been buried for a long period of time and it is not possible to verify the connections visually. In addition, soil with low resistance is often chosen for constructing substations, which can corrode the grid’s metallic components over time. In the “IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Grounding System” (IEEE 81 standard) different methods for measuring the continuity are mentioned. A 230 kV substation was examined using the high-current test method.

Advertising

EPR Android App Banner

High-current test method
In the first step, different reference and test points are identified in the floor plan of the substation. Then the measurements are done. A DC current (ideally 50 A minimum) is injected into the ground grid from a ground riser, it then passes through the grid itself to a reference riser. One part of the current flows to the ground grid while the other part flows above ground to grounded structures. The branch current that flows to the ground grid is measured with a DC clamp meter (Figure 1) in order to determine the resistance of the conductors that are buried between the injection points. The corresponding resistance of the buried conductors is calculated based on the measured branch current and voltage values. In order to compare the resistances of different test points to each other, the distance between the two injection points has to be taken into account. Therefore, the measured resistances are divided by the distance.

A practical experience
The resistances between different reference and test points were measured in the 230 kV substation. The equipment that was used during the test was a CPC 100 for delivering the 300 A DC that was required, a DC voltmeter, a DC clamp ammeter and markers for identifying the test points (Figure 2).The resistances per meter were determined for several test points in the substation as shown in Figure 3. The measurement showed no significant deviations between the relative resistances within the substation. All of the values were between 0.4 m?/m and 1.2 m?/m.

Further investigation is recommended if the test points show a significantly higher resistance value compared with other test points. The test point should be revealed in order to carry out a visual inspection.

In addition to measuring the impedance of the ground grid and the step and touch voltages of the substation, it is also important to be aware of the integrity of the grid itself. An integrity test for verifying the continuity of the grid at any of its points should be a standard procedure in the maintenance strategy of a substation. Thanks to the multi-functionality of the CPC 100, ground impedance, step and touch voltages and integrity tests can be carried out with one test set.

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Android App
Android App
Nirmal Wires
Nirmal Wires
EPR EMagazine February 2025
EPR eMagazine February 2025
EPR eMagazine February 2025

Events

RenewX
RenewX
Wiretech 2025
Wiretech 2025
India Green Energy Expo
India Green Energy Expo

Our Sponsors

Wika
Wika
Ramelex
Ramelex
Ambionics India
Ambionics India
Rayzon Solar Pvt Ltd
Rayzon Solar Pvt Ltd
Om Technical Solutions
Om Technical Solutions
Harting
Harting
CyanConnode
CyanConnode
Hitachi Energy
Hitachi Energy
Doble Engineering
Doble Engineering
CSE Power
CSE Power
ACD Machine Control
ACD Machine Control
Kusam Meco
Kusam Meco
Nirmal
Nirmal
Apar Industries
Apar Industries
Aramco Asia
Aramco Asia
Axis Electrical
Axis Electrical
Meco Instruments Pvt Ltd
Meco Instruments Pvt Ltd
Neo Tele Tronixl Pvt Ltd
Neo Tele Tronixl Pvt Ltd
ZIEHL ABEGG
ZIEHL ABEGG
Paras Wires
Paras Wires
Waa Cables
Waa Cables
Balaji Switchgears
Balaji Switchgears
AEW
AEW
Gloster Cables Limited
Gloster Cables Limited
Cabex India
Cabex India
Newtech Switchgear
Newtech Switchgear
Vsole Solar
Vsole Solar
Ai Earthing
Ai Earthing
Rectifiers & Electronics
Rectifiers & Electronics
Elev8 Lift
Elev8 Lift
Synthesis Winding Technologies Pvt Ltd
Synthesis Winding Technologies Pvt Ltd
flir system
flir system
Omicron
Omicron
CAT
CAT
ATS Group
ATS Group
Ganz Electric
Ganz Electric
Havells
Havells
Eplan
Eplan
Synergy Transformers
Synergy Transformers
Marosons Electricals
Marosons Electricals
Myriad Industrial Solutions
Myriad Industrial Solutions
EMR
EMR
Teknika
Teknika
AVR
AVR
Indian Transformers
Indian Transformers
Triveni Turbine ltd
Triveni Turbine ltd
Ultra Electric India
Ultra Electric India
Polycab
Polycab
Electrotherment
Electrotherment
Minilec Group
Minilec Group